time for our update progress again, yesterday night supposed to have a meeting with the resident manager & consulting firm but to our disappointment both representative fail to turn up and inform everyone last minute where else the meeting been set since week ago,very unprofessional behavior.Anyway forget about my rant let go through so progress update for everyone.
- security clocking will be install by this end of this week, so hopefully now we can see guard doing what their supposed to do.
- after a long hour of discussion wit the security company it seem their behavior is still the same, according to our pak Sahak his observation on those guard rating is still below average, however we are paying them at 4.50 per hour where else Armanee is rm 6 per hour, for time being let monitor again since the information is less then a month.
- intercom supplier have been provided by the JMC member for the RM to get quotation and check the problem but somehow the action have been slow and pending consultant to come over to check the machine problem. No idea when it going to come over to check the system no rm to feedback to us maybe if any expertise out there can help us in this ?
- All access card door have been fix, well after chasing for so long finally it been fix, where else if got people doing their audit job and monitoring those thing will not be spoil and left it undone for so long, hopefully this thing will be maintainable as their charges for one time service is rm 1.7k not cheap consider the amount of frequency the thing spoil, hope resident will not spoil this or try to steal the machine back to their own house (this do happen b4, maybe there are some sick physcho in here)
- MPPJ don't have our building plan, so now we cannot decide on how is the common area and how is the electricity been use, already contacted Daniel Keat (MK Land) will come back to us in two week times (let see)
- AUDIT Account requested by the MK to submit the audited account by 29/May so those with accounting or audit expert or what ever expert please be ready and help to see if and issue on the account
- Good news to all the errant defaulter whom still own the maintenance, sinking fund money, by this week we should have a complete list of debtor from YBR converted into excel, now there given all data in PDF therefore take times to sorted out all the data (have to copy and paste one by one to our own record, damn those people try to make our work difficult only), Anyway subsequent action will those amount outstanding will be posted in notice board if by seven days no changes been make, based on the amount the JMB will issue letter of demand to all this people no more mr nice guys, bare in mind those errant owner will need to bare all the legal charges
- Swimming pool light and the water cascade will get the quotation by next week and proceed with the repair, as JMC first month is to repair all those broken item in common area so fast still alot of thing to do, if anyway have idea, contact or what ever information which will help the JMC run better just drop by to the weekly meeting
- landscaping & housekeeping will have a review with both contractor as their current service is below average, ya we pay below average but still there need to maintain the standard.. those flower and plant is like been in desert country not sure there actually got put in water or fertilizer or not no one monitor , RM don't knew monitor what maybe monitor computer
- electrical consumption in common area is 30k per month have already engage consultant company to check on it for sometimes so far no one come, until our JMB chairman call them there only info we just sent them the work request, what actually happening here i wondering
- there will be some painting activity again for the main lobby seem like waiting for the RM to do work is so slow most of the JMC member decide to help our own building to do some make up